JEDDAH | Jeddah Tower | 1000m+ | 3281ft+ | 167 fl

4 Likes

“The progress of Jeddah Tower continues at an accelerating pace, reaching the 86th floor.”

9 Likes

“Arrival of Jeddah Tower at floor 87 at a rate of one floor every 5 days on 26/1/2026”

7 Likes

Floor 88

"Business communication in #JeddahTower

where the 87th floor has been completed

and ongoing work to install the glass cladding, which is noted for its acceleration”

10 Likes
6 Likes

Based off diagrams, it looks like this is closing in on 1,200 feet

2 Likes
2 Likes

Yup! Around 360 meters (1181 ft) tall now. Almost there upon reaching the height of the ESB :smiley:

2 Likes

“Project Updates Tuesday 10 February 2026 Completion of works on the 89th floor of the tower #جدة Work on the 90th floor has begun. Start Lifting Suites ( 73rd - 75th Floors ) For the actual floors (ceilings and floors of the floors) which are seen as lines across the width of the building, the works exceeded the 70th floor (before the return of the works it was at 48-49) Acceleration of work on exterior glass cladding on all facades”

”February 10, 2026… Start of pouring concrete for the 90th floor at a rate of one floor every 4 days”

8 Likes

And today

364.5 meters

8 Likes

Nearly two feet above Trbovlje Power Station. The mass between the two is unimaginable…yet of course both have different purposes

2 Likes

Jeddah Tower is continuing its growth spurt!! :smiley:

As of now, it’s 1 floor per 5 days

z

Comparison between now and resumption time ^

13 Likes

Just four more floors and this tower will be slightly over three feet above the mooring mast of the Empire State Building, excluding the additional spire

2 Likes

Even better, glass facade installation is continuing. I’ve been waiting for a long time for the facade to continue taking shape past the base, pre-pandemic years I believe. :building_construction:

3 Likes

Officially over 1200ft!!!

"Project Updates

And as I said 4 months ago, it would be between 91 - 93 floors by the start of Ramadan month, today work begins on floor 92

Monday, February 16, 2026

Height: 368.5 meters

Completion of work on (floor 91) of #Jeddah Tower and start of work on (floor 92)

Start of lifting the wings for the (floors 73 - 75)

As for the actual floors (ceilings and floors of the levels) that you see as lines across the width of the building, the work has exceeded floor 72 (before resuming work, it was at 48-49)

Acceleration of work on the external glass claddings on all facades”

13 Likes

I remember first joining skyscraper groups around the time the Burj Khalifa went up, amazed at the ability to build such a tall structure! 15+ years later, we’re now seeing Jeddah Tower take shape that’ll be even taller than that! :exploding_head:

Whereas Dubai had TONS of construction all over the city, has building this tower helped spur any other big developments (or at least any planning for other skyscrapers) in the area? :thinking:

Looking at details regarding the “Jeddah Economic City” mass development on Wikipedia and elsewhere, it seems this will be the only major tower developed for now…?

4 Likes

“**Highlights of Jeddah Tower 2026**

It has become the tallest tower in Jeddah and the third tallest tower in Saudi Arabia.
Work is progressing at an accelerated pace, with reaching the 100th floor by March 2026.

The tower, which will exceed 1,000 meters, is expected to be fully completed by 2028.”

3 Likes