At this stage, we should see the next floor poured within 1-2 weeks. Then another floor poured every 7-10 days, if there are no snags and everything goes well.
At this stage, we should see the next floor poured within 1-2 weeks. Then another floor poured every 7-10 days, if there are no snags and everything goes well.
My last post was premature. They can’t start going vertical again yet until they attain revised construction permits. They have applied for the permits, but they haven’t been issued yet.