NEW YORK | Gateway Project (Hudson Rail Tunnel)

Looks like some of the temporary access bridges are being dismantled. This is a good indicator that things are wrapping up.

At Tonnelle Avenue, the final segment is now receiving the road deck concrete. This will be done by the end of the year.

In New York, the slurry wall construction is well underway, and the Hudson Yards casing is almost fully excavated. Unfortunately, the camera there stopped updating, so I can’t provide snapshots of the latest activity. However, the HYCC-3 camera is able to see the project. Some of the first sections of rebar for the shaft walls are being assembled as well.

There’s now going to be Sunday construction activity, which should help accelerate the HYCC-3 project as well, with work on the waterproof lining and concrete formwork expected to occur during the daytime, along with some residual rock excavation.

And with the groundwater stabilization project, the cofferdam is slowly shifting towards the NYC shore, where the next section of ground will be reinforced and stabilized, and another set of barges is being used to remove abandoned piles left in the water.

17 Likes

Here’s an official NJT update showing progress on the bridge from December 2022 to June 2025.

6 Likes

That’s awesome progress! But, man, that stock music gets old really fast.

1 Like

Here’s an update concerning the Palisades shaft. The Gateway program announced that 14 out of 42 segments of the shaft have been installed. They’ve almost got half of them installed so far. This photo was published with the announcement on twitter.

17 Likes

Ventilation yes?

13 Likes

Amtrak has recently announced that they are beginning preparation work for the activation of the new Portal Bridge. Additional trackage and turnouts are now being constructed which will help make the transition to the new bridge easier. The photos they released below show some new stuff they are currently doing. Looks like there will be tracks under the NJ Turnpike bridge too.

12 Likes

Good to see the progress being made on the Gateway Project.

I follow this Gateway project and applaud and support the great work these folks are doing to improve our infrastructure here in the US of A. However, I closely follow the latest and greatest worldwide regarding our built environment; and it must be said that the USA is lagging behind in all things construction related.

This is just one example of where construction technology is regarding bridge construction: and this is a perfect opportunity to look at the stark comparisons. I have also posted similar comparisons regarding the construction of buildings here in the USA compared to other countries.

I find this type of information helpful; and hope you will find this video enlightening and enjoyable.

3 Likes

This is most likely what the trench is for. They recently buried utilities.

In other news:

A contractor wants to try and temporarily pause bidding for the new NEC viaduct because they want to take part in it and while they were one of the candidates shortlisted, a union representative was not included in the labor agreement. This would delay the start date for the viaduct that connects the NEC to the new tunnels.

7 Likes

The deck for the 3rd piece of Tonnelle Avenue’s bridge is complete. Work is now shifting to building the walls, with the last pieces being the anti-suicide fencing, which comes after the walls are cast.

Kyle Tillyer recently flew his drone by the Portal Bridge, giving us excellent visuals of the bridge, which is rapidly nearing completion.

https://www.instagram.com/p/DR0cGXTgQq7/

I have yet to figure out what is going on here but they’re now pouring concrete on what looks like some kind of scaffolding structure. I wouldn’t doubt that this is for the TBMs which are still set to arrive early next year.

The Gateway Program also published some photos showing various projects.

Palisades Tunnel:

Tonnelle Avenue:

Manhattan Shaft:

Hudson Yards Casing 3:

21 Likes
7 Likes