Forgive me if this has been answered or is part of coverage previously reported, but are the TBM’s being assembled by Herrenknecht people or the GC?
The GDC workers are assembling the TBMs. Herrenknecht built them and assembled them for testing in Germany before they broke them back down, packed the components into containers, and shipped them here. However, I would not be surprised if they have engineers providing oversight, ensuring they are assembled correctly and work, though.
Got it. TY
As the TBM is progressing, tunnel liners have been going up. The support structure not only helps advance the TBM, but there are additional supports installed to ensure stability of the tunnel liner. When the tunnel is done, that section will be filled in and a proper tunnel entrance constructed. At this current point, the entire cutter head and shield are now inside the rock face.
While all the focus is on the new tunnels, another major event happened: the Old Portal Bridge has officially closed. Work has commenced to start shifting all train traffic to the new Portal Bridge, and once the new bridge is fully in service, the old bridge will be torn down.
Picture from Amtrak:
I don’t think anyone will miss that bridge.
The Old Portal Bridge’s catenary poles are coming down. Work is at full speed ahead with the decommissioning of the old bridge. Every so often, NJ Transit and Amtrak provide photos showing what’s going on. This work is significant because these towers are what carry the old bridge’s signaling and high-voltage cables.
The 2nd TBM is also nearly complete. The crane that was used to assemble the heavy and large components has been dismantled, and one of the last segments of the TBM is being assembled before it is connected to the rest of the unit. As the machine is being assembled, the shipping containers the parts came in are being removed as well, to make room for the tunnel liner segments necessary for each tunnel.
Signals on the Portal Bridge 2nd track are also being tested, as workers continue to connect the track to existing infrastructure.
Do we think, once they demolish the old portal bridge, they will start work on the second new bridge? Or that isn’t a priority for them?
The second bridge hasn’t even been funded yet nor are there any announcements regarding it. It isn’t happening anytime soon.
Knew you’d have the answer.
Booo to no second bridge. If there is ever an issue with one track on that bridge, it becomes another choke point in the always awful NJ transit northeast corridor line.
I have noticed that looking side to side that the two TBMs are mirror images of each other. Does anyone know what that is for? Could it be related to provisions that have to be made for the connector tunnels that will link the two tunnels together?
The new bridge should hopefully be more reliable and track problems not a common occurence.
@billw As for the mirrored TBMs, I am not sure what the exact reason for why they are like that. The TBMs do not have any hardware on the sides for excavating the pass-throughs. Those may be built via alternative means.
A more realistic justification for mirroring is that since all the power, water and other conduits are along the sides of the launch box, mirroring them means all the connections needed to power the TBMs are accessible.
Sounds plausible.
NJ Transit has provided another Portal Bridge update. Latest happenings include more work on the 2nd track and the removal of catenary and electric lines on the old bridge.
I got another awesome Portal Bridge cutover update to share. Since I actively follow the work, I saw a post by one of the contractors showing off some of the work they are doing. This series of updates by one of the contractors, Taylor Bros, involves the replacement of part of a viaduct with precast sections.
As for tunneling, the 2nd TBM is nearly complete, and the 1st TBM is making good progress, with about half the machine already inside the Palisades.
More updates from the Portal Bridge project from an Amtrak Press Release:
And here are some updates from NJ Transit as well:
There won’t be any more updates from the Portal Bridge page on NJ Transit since the live cams have been fully deactivated and taken down.
I also found a video someone took that shows the progress from a train. The video is reversed to give viewers a perspective of what it looks like going to Secaucus.
Another video is from the perspective of a passenger from their seat:
One of the most significant things is that the catenary has been fully removed from the old bridge, and work is underway to disconnect the high-voltage transmission lines. Once these lines are down, demolition can commence on the old bridge. Work is already underway to remove the trackage, with the entire old bridge cut off from the NEC on both sides.
Someone seems to have clauded up a website to follow the project: https://hudson.tube/
It’s a pretty good tracker tbh and nicely collects the cameras in one spot.
Here’s a video from the GDC showing the TBM placing tunnel segments.
The 1st TBM is almost fully into the ground, and TBM 2 is just about ready to launch.
And, in Hudson County, micropile installation is progressing to help support the bridge due to eventual tunneling for the Hudson River segment.
Great find! Shoutout to whoever made this.